On the construction site of one of the expressway sections, a conflict arose between the General Contractor and the contractor responsible for earthworks. The point of contention was the quantity of earthworks completed. The figures presented by the contractor showed a significantly higher amount of work to be invoiced, which the General Contractor disagreed with. We were tasked with conducting a detailed measurement of the work, for which we used a photogrammetric control network and the Trimble UX5 unmanned aerial vehicle. As is often the case, the truth lay... somewhere in between.